Brook Lodge Farm, Isfield

New-build Passivhaus home | Cowan Architects: Stage 3 planning amendments and Stage 4 technical design | Stage 5 delivery: Awen Design

The Brief

The client already had planning permission for a new house in the paddock opposite their home. Under the planning consent, their existing home would be demolished once the new house was finished. The approved design came from Nicolas Pople Architects. It had not been designed as a Passivhaus. When the client decided to go for Passivhaus, they appointed Cowan Architects to see whether the scheme could get there and to rework it.

Reworking the design for Passivhaus

Our first review found weaknesses in thermal bridging, airtightness and form factor. The wall, floor and roof build-ups were also too thin, and the orientation wasn’t ideal. We reduced the overhangs and the amount of glazing, reviewed the building’s orientation, and based the envelope on MBC Timber Frame’s Passivhaus system. We ran the PHPP energy model through a rigorous iterative process, so we could show early that the design could comply before technical design began. We then prepared and submitted the planning amendments needed for these changes.

Responding to the site

The site was an untouched paddock beside a brook with pluvial surface water issues causing the site to be prone to flooding.  Consequently, we set the house slightly above the surrounding ground and added a gravel drainage channel around its edge. This protects the building and keeps the slab detailing simple.

Technical design and tender information
At Stage 4 we produced the full technical design and a detailed tender package such that our tender specification covered:

  • Envelope: MBC insulated foundation and timber frame, Western Red Cedar shingles on the walls and roof, Vandersanden brick slips, and VMZinc seamed zinc on the dormers and feature bays
  • Windows: triple-glazed windows and doors from Ecohaus
  • Energy systems: in-roof solar PV and an air source heat pump
  • Interiors: a polished screed ground floor, with birch plywood specified for the joinery, internal doors and a feature ceiling in the living area
  • Stair: a crafted stair whose treads and risers are made from reclaimed oak parquet blocks, set against a curved wall of oak battens

Delivery

Awen Design delivered the project at Stage 5, through construction to completion.

What we learned

Passivhaus works best when it’s the starting point, not something added later. Bringing it in after planning is possible, but it takes rework that could have been avoided. The RIBA and Passivhaus Trust’s Passivhaus Overlay to the Plan of Work sets out which decisions need to be made at each stage, from Stage 0 to 7. We’d recommend it to any client thinking about Passivhaus.

📸 Photography: Mary Gaudin

At Cowan Architects, We Get It Right First Time.

CLIENT
Private

LOCATION
Isfield

RIBA STAGES
3-4

VALUE
Confidential

CONSULTANCY
Architects / Passivhaus Designers